Accuform - Project report [D:\B-SIM Testy\test\Project1k_new.tff]
Generated by B-SIM Version 2.35, 21. October 2002, 15:57:05.

Basic information

Project name D:\B-SIM Testy\test\Project1k_new.tff
Solver start 21. October 2002, 15:56:19
Solver duration 00:00:46
Solution type Full solution
Solver result Simulation completed successfully

Project source files

FEM grid D:\B-SIM Testy\test\FEM1k.bcs
Tools [01] D:\B-SIM Testy\test\ToolL.tol
[02] D:\B-SIM Testy\test\ToolR.tol
[02 tool(s) used.]
Process control D:\B-SIM Testy\test\AWT-100-0-100-0-PWT-50.pct
Material D:\B-SIM Testy\test\HDPE.VIE
Heat and friction D:\B-SIM Testy\test\Heat.hfr

Additional project information

Job number #
Programmer
Comments

FEM grid details

Basic information

Number of elements 896 Number of nodes 462

Initial dimmensions
(mm)

X min: -40
X max: 40

Y min: -40
Y max: 40
Z min: 0
Z max: 300

Final dimmensions
(mm)

X min: -75.1
X max: 40

Y min: -59.6
Y max: 59.6
Z min: 1.13
Z max: 300

 

Generated by B-SIM Version 2.35, 21. October 2002, 15:57:05.